Design and manage procurement route
Contents |
[edit] Introduction
The design and manage procurement route shares several characteristics of management contracting.
Under this arrangement, the works are constructed by a number of different works contractors who report to a management contractor who is selected early in the process. The management contractor assumes responsibility for the other contractors and the design team. This procurement approach is suitable for large, complex projects or fast track projects.
It may also be a preferred method when the client wishes to have one point of contact who is responsible for everything. A single point of contact is also the case with the design and build procurement route, although some clients feel this route is only appropriate for simple projects where design quality is not the first priority.
[edit] Variations
There are two common variations of the design and manage procurement route:
- The organisation is paid to design and manage the work and delivers the project by hiring subcontractors to design and construct the project.
- The organisation is paid as a consultant to act as the agent of the client to design and manage the work by obtaining subcontract tenders from works contractors who then each enter into a direct contract with the client.
[edit] Advantages and disadvantages
Potential benefits to the design and manage procurement route include:
- A collaborative relationship between the design and manage contractor and the client.
- Fewer delays caused by a lack of information or miscommunication.
- Clearer delineation of overall financial responsibilities for the default of sub-contractors.
Possible negative aspects of the design and manage procurement process include:
- The duplication of resources between trade contractors and the design and manage contractor, resulting in a higher prices.
- A lack of an established contract sum, resulting in an estimate created by the quantity surveyor and then endorsed by the design and manage contractor; it is then confirmed along the way as tendering progresses and the works proceed.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIOB photography competition is open for entries.
ECA Edmundson apprentice of the year award
Finalists announced.
Major new study exposes serious knowledge gaps.
Generating energy from internal light as well as sunshine.
ECA welcomes plans to strengthen subcontractor quality control.
Combining mid-career qualifications with experience broadens career opportunities.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.