Design and manage procurement route
Contents |
[edit] Introduction
The design and manage procurement route shares several characteristics of management contracting.
Under this arrangement, the works are constructed by a number of different works contractors who report to a management contractor who is selected early in the process. The management contractor assumes responsibility for the other contractors and the design team. This procurement approach is suitable for large, complex projects or fast track projects.
It may also be a preferred method when the client wishes to have one point of contact who is responsible for everything. A single point of contact is also the case with the design and build procurement route, although some clients feel this route is only appropriate for simple projects where design quality is not the first priority.
[edit] Variations
There are two common variations of the design and manage procurement route:
- The organisation is paid to design and manage the work and delivers the project by hiring subcontractors to design and construct the project.
- The organisation is paid as a consultant to act as the agent of the client to design and manage the work by obtaining subcontract tenders from works contractors who then each enter into a direct contract with the client.
[edit] Advantages and disadvantages
Potential benefits to the design and manage procurement route include:
- A collaborative relationship between the design and manage contractor and the client.
- Fewer delays caused by a lack of information or miscommunication.
- Clearer delineation of overall financial responsibilities for the default of sub-contractors.
Possible negative aspects of the design and manage procurement process include:
- The duplication of resources between trade contractors and the design and manage contractor, resulting in a higher prices.
- A lack of an established contract sum, resulting in an estimate created by the quantity surveyor and then endorsed by the design and manage contractor; it is then confirmed along the way as tendering progresses and the works proceed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.